  "id": "lot-dex16-ar-or-l1",
  "lot_id": "lot-dex16-ar-or-l1",
  "name": "Arad – Oradea Lot 1: Oradea – Salonta",
  "lot_name": "Arad – Oradea Lot 1: Oradea – Salonta",
  "road_id": "dex16",
  "road_ref": "DEx16",
  "road_name": "DEx16 Drumul Expres Arad – Oradea – A3 (Biharia)",
  "section_id": "sec-dex16-ar-or",
  "section_name": "Arad – Oradea",
  "length_km": 33.7,
  "open_km": 0,
  "profile": "expressway",
  "contractor": "Asocierea Precon Transilvania SRL – Automagistral Pivden SRL",
  "contract_value": "2.32 mld. lei fără TVA",
  "financing": "Programul Transport 2021–2027 (execuție); POIM 2014–2020 (proiectare)",
  "tender_stage": "contract_signed",
  "progress_percent": 0,
  "contractual_date": "2027-03-01",
  "estimated_date": "2029",
  "actual_date": null,
  "status": "design",
  "status_label": "În proiectare",
  "status_detail": "În proiectare: 33,7 km",
  "bbox": [
    21.694064,
    46.793251,
    21.880757,
    47.07272
  ],
  "claims": [
    {
      "id": "clm-7efe2872aba6",
      "claim_type": "contract_value",
      "date_type": null,
      "value": "2320000000 RON",
      "quote": "Contractul, cu o valoare de 2,32 de miliarde de lei (fără TVA)",
      "url": "https://www.economica.net/drumul-expres-arad-oradea-2_992876.html",
      "source": "Economica.net",
      "source_name": "Economica.net",
      "tier": 2,
      "date": "2026-11-07",
      "approved_at": "2026-11-09T12:40:50.056Z"
    },
    {
      "id": "clm-268b791a5cc8",
      "claim_type": "financing",
      "date_type": null,
      "value": "PT",
      "quote": "finanțat prin Programul Transport (PT) 2021 – 2027",
      "url": "https://www.economica.net/drumul-expres-arad-oradea-2_992876.html",
      "source": "Economica.net",
      "source_name": "Economica.net",
      "tier": 2,
      "date": "2026-11-07",
      "approved_at": "2026-11-07T21:10:53.489Z"
    },
    {
      "id": "clm-0d214a3383bc",
      "claim_type": "opening_date",
      "date_type": "estimated",
      "value": "2028",
      "quote": "Termen de deschidere: 2028 pentru Loturile 1 și 2",
      "url": "https://economedia.ro/drum-expres-arad-oradea-autoritatile-incep-exproprierile-pe-traseul-din-judetul-arad.html",
      "source": "Economedia",
      "source_name": "Economedia",
      "tier": 2,
      "date": "2025-10-08",
      "approved_at": "2026-11-06T16:48:56.294Z"
    },
    {
      "id": "clm-e6a17eee4b2e",
      "claim_type": "contract_value",
      "date_type": null,
      "value": "2320000000 RON",
      "quote": "Contract semnat în data de 28 mai 2025 cu Precon pentru 2,32 mld lei",
      "url": "https://hotnews.ro/drum-expres-de-la-oradea-la-arad-contract-semnat-pentru-ultimul-lot-care-nu-avea-constructor-care-este-termenul-de-finalizare-harta-2160835",
      "source": "HotNews",
      "source_name": "HotNews",
      "tier": 2,
      "date": "2026-01-29",
      "approved_at": "2026-11-06T16:48:56.294Z"
    }
  ],
  "stories": [
    {
      "id": "sc-13272b7b5a9f",
      "title": "Ucrainenii care intră anul viitor pe Drumul Expres Arad – Oradea: România traversează în prezent un adevărat avânt în…",
      "extracted_headline": "Contract semnat pentru Lotul 1 al Drumului Expres Arad–Oradea; lucrările programate din primăvara 2027",
      "summary": "Asocierea PRECON TRANSILVANIA – AUTOMAGISTRAL PIVDEN a câștigat și a semnat contractul pentru Lotul 1 (33,7 km) al Drumului Expres Arad–Oradea, proiect finanțat prin Programul Transport 2021–2027.",
      "url": "https://www.economica.net/drumul-expres-arad-oradea-2_992876.html",
      "published_at": "2026-11-07T15:07:14Z",
      "roads": [
        "DEx16"
      ],
      "lot_id": "lot-dex16-ar-or-l1",
      "lot_ids": [
        "lot-dex16-ar-or-l1"
      ],
      "source": {
        "id": "economica",
        "name": "Economica.net",
        "trust_tier": 2
      },
      "co_citations": []
    },
    {
      "id": "sc-133539ce947b",
      "title": "Încep lucrările la Drumul Expres Arad-Oradea",
      "extracted_headline": "Încep lucrările pregătitoare pentru Drumul Expres Arad–Oradea, lucrări estimate sfârșitul oct. 2026",
      "summary": "Lucrările pregătitoare pentru Drumul Expres Arad–Oradea sunt programate să înceapă la finalul lunii octombrie 2026, cu activități de delimitare a culoarului și cercetări arheologice.",
      "url": "https://economedia.ro/incep-lucrarile-la-drumul-expres-arad-oradea-asocierea-onur-straco-intra-pe-traseu-de-la-finalul-lunii-octombrie.html",
      "published_at": "2026-10-06T17:00:07Z",
      "roads": [
        "DEx16"
      ],
      "lot_id": "lot-dex16-ar-or-l1",
      "lot_ids": [
        "lot-dex16-ar-or-l1",
        "lot-dex16-ar-or-l3"
      ],
      "source": {
        "id": "economedia",
        "name": "Economedia",
        "trust_tier": 2
      },
      "co_citations": []
    },
    {
      "id": "sc-70e6955f11bf",
      "title": "Drumul Expres Arad - Oradea. Exproprierile de pe traseu se vor încheia cu proprietarii din Şimand şi Chişineu-Criş /…",
      "extracted_headline": "Exproprierile pentru Drumul Expres Arad–Oradea se apropie de final; contracte de execuție semnate pentru toate loturile",
      "summary": "DRDP Timişoara anunță că procedura de expropriere pentru Drumul Expres Arad–Oradea se va finaliza prin întâlniri la Şimand şi Chişineu‑Criş.",
      "url": "https://economedia.ro/drumul-expres-arad-oradea-exproprierile-de-pe-traseu-se-vor-incheia-cu-proprietarii-din-simand-si-chisineu-cris-cand-vor-incepe-lucrarile.html",
      "published_at": "2026-04-20T13:37:08Z",
      "roads": [
        "DEx16"
      ],
      "lot_id": "lot-dex16-ar-or-l1",
      "lot_ids": [
        "lot-dex16-ar-or-l1",
        "lot-dex16-ar-or-l2",
        "lot-dex16-ar-or-l3"
      ],
      "source": {
        "id": "economedia",
        "name": "Economedia",
        "trust_tier": 2
      },
      "co_citations": []
    },
    {
      "id": "sc-5467995db1cb",
      "title": "Drum expres de la Oradea la Arad: Contract semnat pentru ultimul lot care nu avea constructor / Care este termenul de…",
      "extracted_headline": "Contract semnat pentru Lotul 3 din Drumul Expres Oradea–Arad; termen de finalizare 24 luni",
      "summary": "Contractul pentru Lotul 3 (47,07 km) al drumului expres Oradea–Arad a fost semnat, astfel întreaga șosea de 120 km are constructor.",
      "url": "https://hotnews.ro/drum-expres-de-la-oradea-la-arad-contract-semnat-pentru-ultimul-lot-care-nu-avea-constructor-care-este-termenul-de-finalizare-harta-2160835",
      "published_at": "2026-01-29T12:29:12Z",
      "roads": [
        "DEx16"
      ],
      "lot_id": "lot-dex16-ar-or-l1",
      "lot_ids": [
        "lot-dex16-ar-or-l1",
        "lot-dex16-ar-or-l2",
        "lot-dex16-ar-or-l3"
      ],
      "source": {
        "id": "hotnews",
        "name": "HotNews",
        "trust_tier": 2
      },
      "co_citations": []
    },
    {
      "id": "sc-6e441b79bde2",
      "title": "Drumul Expres Arad-Oradea. CNAIR a semnat contractul pentru construcția primului lot cu o asociere de constructori…",
      "extracted_headline": "CNAIR a semnat contractul pentru Lotul 1 (Oradea–Salonta) din DEx16 cu asociere româno‑ucraineană",
      "summary": "CNAIR a semnat contractul pentru construcția primului lot (Oradea–Salonta) din Drumul Expres Arad–Oradea cu o asociere româno‑ucraineană.",
      "url": "https://economedia.ro/drumului-expres-arad-oradea-cnair-a-semnat-contractul-pentru-constructia-primului-lot-cu-o-asociere-de-constructori-romani-si-ucraineni.html",
      "published_at": "2025-05-15T12:33:02Z",
      "roads": [
        "DEx16"
      ],
      "lot_id": "lot-dex16-ar-or-l1",
      "lot_ids": [
        "lot-dex16-ar-or-l1",
        "lot-dex16-ar-or-l2",
        "lot-dex16-ar-or-l3"
      ],
      "source": {
        "id": "economedia",
        "name": "Economedia",
        "trust_tier": 2
      },
      "co_citations": []
    }
  ],
  "provenance": {
    "contract_value": {
      "source": "Economica.net",
      "tier": 2,
      "url": "https://www.economica.net/drumul-expres-arad-oradea-2_992876.html",
      "quote": "Contractul, cu o valoare de 2,32 de miliarde de lei (fără TVA)",
      "date": "2026-11-07"
    },
    "financing": {
      "source": "Economica.net",
      "tier": 2,
      "url": "https://www.economica.net/drumul-expres-arad-oradea-2_992876.html",
      "quote": "finanțat prin Programul Transport (PT) 2021 – 2027",
      "date": "2026-11-07"
    },
    "estimated_date": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/drum-expres-arad-oradea-autoritatile-incep-exproprierile-pe-traseul-din-judetul-arad.html",
      "quote": "Termen de deschidere: 2028 pentru Loturile 1 și 2",
      "date": "2025-10-08"
    },
    "progress_percent": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/drumului-expres-arad-oradea-cnair-a-semnat-contractul-pentru-constructia-primului-lot-cu-o-asociere-de-constructori-romani-si-ucraineni.html",
      "quote": "CNAIR a semnat joi, 15 mai, contractul pentru construcția primului lot (Oradea – Salonta)",
      "date": "2025-05-15"
    },
    "contractor": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/drumului-expres-arad-oradea-cnair-a-semnat-contractul-pentru-constructia-primului-lot-cu-o-asociere-de-constructori-romani-si-ucraineni.html",
      "quote": "CNAIR a semnat joi, 15 mai, contractul pentru construcția primului lot (Oradea – Salonta)",
      "date": "2025-05-15"
    },
    "contractual_date": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/drumului-expres-arad-oradea-cnair-a-semnat-contractul-pentru-constructia-primului-lot-cu-o-asociere-de-constructori-romani-si-ucraineni.html",
      "quote": "CNAIR a semnat joi, 15 mai, contractul pentru construcția primului lot (Oradea – Salonta)",
      "date": "2025-05-15"
    },
    "status": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/drumului-expres-arad-oradea-cnair-a-semnat-contractul-pentru-constructia-primului-lot-cu-o-asociere-de-constructori-romani-si-ucraineni.html",
      "quote": "CNAIR a semnat joi, 15 mai, contractul pentru construcția primului lot (Oradea – Salonta)",
      "date": "2025-05-15"
    }
  },
  "attributed_range": null,
  "is_hand_drawn": false
}