  "id": "lot-a3-iernut-chetani",
  "lot_id": "lot-a3-iernut-chetani",
  "name": "Iernut – Chețani",
  "lot_name": "Iernut – Chețani",
  "road_id": "a3",
  "road_ref": "A3",
  "road_name": "A3 Autostrada Transilvania (București – Ploiești – Brașov – Cluj – Borș)",
  "section_id": "sec-a3-tgm-cluj",
  "section_name": "Târgu Mureș – Câmpia Turzii – Gilău – Nădășelu",
  "length_km": 17.9,
  "open_km": 17.9,
  "profile": "motorway",
  "contractor": "Asocierea Astaldi – Max Bögl",
  "contract_value": "437.63 mil. lei (fără TVA)",
  "financing": "Fondul de Coeziune (POIM) / Buget de stat",
  "tender_stage": "work_commenced",
  "progress_percent": null,
  "contractual_date": "2017-07",
  "estimated_date": null,
  "actual_date": "2020-09-18",
  "status": "open",
  "status_label": "Deschis",
  "status_detail": "Deschis: 17,9 km",
  "bbox": [
    24.074682,
    46.430184,
    24.294419,
    46.459266
  ],
  "claims": [],
  "stories": [],
  "provenance": {
    "progress_percent": {
      "source": "HotNews",
      "tier": 2,
      "url": "https://hotnews.ro/stiri-infrastructura_articole-24291986-autostrada-deschisa-transilvania-iernut-chetani-inaugurare.htm",
      "quote": "Vineri, 18.09.2020, începând cu ora 18:00, se va deschjde circulația rutieră pe sectorul de autostradă Iernut – Chetani",
      "date": "2020-09-18"
    },
    "contractor": {
      "source": "G4Media",
      "tier": 2,
      "url": "https://www.g4media.ro/video-inca-18-kilometri-din-autostrada-transilvania-intra-in-circulatie-tronsonul-iernut-chetani-este-gata-dupa-4-ani-de-lucrari.html",
      "quote": "A3 Iernut – Chețani – 17,9 km Constructor: asocierea ASTALDI SPA – MAX BOEGL ROMANIA SRL – ASTALROM SA – CONSITRANS SRL Contract: semnat în 2015, ordinul de începere a lucrărilor dat în 2016",
      "date": "2020-09-18"
    },
    "contract_value": {
      "source": "G4Media",
      "tier": 2,
      "url": "https://www.g4media.ro/video-inca-18-kilometri-din-autostrada-transilvania-intra-in-circulatie-tronsonul-iernut-chetani-este-gata-dupa-4-ani-de-lucrari.html",
      "quote": "Stadiu fizic (aprilie 2020): 88,99% Valoare contract (fără TVA): 437,6 mil. lei",
      "date": "2020-09-18"
    },
    "financing": {
      "source": "G4Media",
      "tier": 2,
      "url": "https://www.g4media.ro/video-inca-18-kilometri-din-autostrada-transilvania-intra-in-circulatie-tronsonul-iernut-chetani-este-gata-dupa-4-ani-de-lucrari.html",
      "quote": "asigura finantarile Banii de cofinantare zboara la pomeni si o sa pierdem toti banii europeni aprobati deja",
      "date": "2020-09-18"
    },
    "contractual_date": {
      "source": "G4Media",
      "tier": 2,
      "url": "https://www.g4media.ro/video-inca-18-kilometri-din-autostrada-transilvania-intra-in-circulatie-tronsonul-iernut-chetani-este-gata-dupa-4-ani-de-lucrari.html",
      "quote": "Contract: semnat în 2015, ordinul de începere a lucrărilor dat în 2016",
      "date": "2020-09-18"
    },
    "actual_date": {
      "source": "HotNews",
      "tier": 2,
      "url": "https://hotnews.ro/stiri-infrastructura_articole-24291986-autostrada-deschisa-transilvania-iernut-chetani-inaugurare.htm",
      "quote": "Vineri, 18.09.2020, începând cu ora 18:00, se va deschjde circulația rutieră pe sectorul de autostradă Iernut – Chetani",
      "date": "2020-09-18"
    },
    "status": {
      "source": "HotNews",
      "tier": 2,
      "url": "https://hotnews.ro/stiri-infrastructura_articole-24291986-autostrada-deschisa-transilvania-iernut-chetani-inaugurare.htm",
      "quote": "Vineri, 18.09.2020, începând cu ora 18:00, se va deschjde circulația rutieră pe sectorul de autostradă Iernut – Chetani",
      "date": "2020-09-18"
    }
  },
  "attributed_range": null,
  "is_hand_drawn": false
}