  "id": "lot-a13-l4",
  "lot_id": "lot-a13-l4",
  "name": "Lotul 4: Sâmbăta de Sus – Făgăraș",
  "lot_name": "Lotul 4: Sâmbăta de Sus – Făgăraș",
  "road_id": "a13",
  "road_ref": "A13",
  "road_name": "A13 Autostrada Carpaților (Sibiu – Făgăraș – Brașov – Bacău)",
  "section_id": "sec-a13-sb-fag",
  "section_name": "Sibiu (Boița) – Făgăraș",
  "length_km": 16.26,
  "open_km": 0,
  "profile": "motorway",
  "contractor": "Asocierea Makyol Insaat Sanayi Turizm ve Ticaret A.S. – Yapi Merkezi Insaat ve Sanayi A.S.",
  "contract_value": "1.19 mld. lei (fără TVA)",
  "financing": "Programul Transport 2021–2027",
  "tender_stage": "work_commenced",
  "progress_percent": 42.61,
  "contractual_date": "2028",
  "estimated_date": "2027",
  "actual_date": null,
  "status": "construction",
  "status_label": "În execuție",
  "status_detail": "În execuție: 16,3 km",
  "bbox": [
    24.823308,
    45.785946,
    25.006548,
    45.808583
  ],
  "claims": [
    {
      "id": "clm-9021e34dd405",
      "claim_type": "progress_percent",
      "date_type": null,
      "value": "36.3",
      "quote": "Tronsonul 4 (Sâmbăta de Sus – Municipiul Făgăraș), în lungime de 16,27 km: stadiul fizic este de 36,26%",
      "url": "https://www.economica.net/autostrada-a13-sibiu-fagaras-28_979643.html",
      "source": "Economica.net",
      "source_name": "Economica.net",
      "tier": 2,
      "date": "2026-09-24",
      "approved_at": "2026-11-06T16:48:56.294Z"
    },
    {
      "id": "clm-edf995dc1863",
      "claim_type": "opening_date",
      "date_type": "estimated",
      "value": "2027-12",
      "quote": "în funcție de vreme, să avem șanse să încheiem lucrarea undeva la sfârșitul lui 2027",
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-a-ajuns-la-45-relocarile-de-gaze-si-vremea-principalele-provocari-ale-santierului.html",
      "source": "Economedia",
      "source_name": "Economedia",
      "tier": 2,
      "date": "2026-11-02",
      "approved_at": "2026-11-06T15:30:10.114Z"
    },
    {
      "id": "clm-2c7849e42fa8",
      "claim_type": "opening_date",
      "date_type": "contractual",
      "value": "2028-01",
      "quote": "Termenul de finalizare, conform contractului ... este ianuarie 2028.",
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-toate-cele-26-de-structuri-sunt-in-lucru-doua-poduri-in-arc-de-164-de-metri-provocarile-proiectului.html",
      "source": "Economedia",
      "source_name": "Economedia",
      "tier": 2,
      "date": "2026-11-03",
      "approved_at": "2026-11-06T12:24:31.271Z"
    },
    {
      "id": "clm-9a897c069b72",
      "claim_type": "contractor",
      "date_type": null,
      "value": "Makyol",
      "quote": "contractului încheiat între CNAIR și constructorul tuc Makyol",
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-toate-cele-26-de-structuri-sunt-in-lucru-doua-poduri-in-arc-de-164-de-metri-provocarile-proiectului.html",
      "source": "Economedia",
      "source_name": "Economedia",
      "tier": 2,
      "date": "2026-11-03",
      "approved_at": "2026-11-06T12:24:31.271Z"
    },
    {
      "id": "clm-9e166fcb1203",
      "claim_type": "opening_date",
      "date_type": "estimated",
      "value": "2027",
      "quote": "să avem șanse să încheiem lucrarea undeva la sfârșitul lui 2027",
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-a-ajuns-la-45-relocarile-de-gaze-si-vremea-principalele-provocari-ale-santierului.html",
      "source": "Economedia",
      "source_name": "Economedia",
      "tier": 2,
      "date": "2026-11-02",
      "approved_at": "2026-11-06T12:24:31.271Z"
    },
    {
      "id": "clm-2e4c9c1644ea",
      "claim_type": "progress_percent",
      "date_type": null,
      "value": "45",
      "quote": "Lotul 4 al autostrăzii A13 Sibiu–Făgăraș ... a ajuns la un stadiu fizic de 45%",
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-a-ajuns-la-45-relocarile-de-gaze-si-vremea-principalele-provocari-ale-santierului.html",
      "source": "Economedia",
      "source_name": "Economedia",
      "tier": 2,
      "date": "2026-11-02",
      "approved_at": "2026-11-05T09:40:53.039Z"
    }
  ],
  "stories": [
    {
      "id": "sc-666dadaf9546",
      "title": "VIDEO: Lotul 4 al Autostrăzii A13 Sibiu-Făgăraș a ajuns la 45%. Relocările de gaze și vremea, principalele provocări…",
      "extracted_headline": "Lotul 4 al A13 Sibiu‑Făgăraș atinge 45% din stadiul fizic, cu provocări meteorologice și relocări de gaze",
      "summary": "Lucrările la lotul 4 al autostrăzii A13 Sibiu‑Făgăraș au ajuns la 45% din stadiul fizic, dar condiţiile meteo şi mutarea reţelelor de gaze încetinesc progresul.",
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-a-ajuns-la-45-relocarile-de-gaze-si-vremea-principalele-provocari-ale-santierului.html",
      "published_at": "2026-11-02T12:55:59Z",
      "roads": [
        "A13"
      ],
      "lot_id": "lot-a13-l4",
      "lot_ids": [
        "lot-a13-l4"
      ],
      "source": {
        "id": "economedia",
        "name": "Economedia",
        "trust_tier": 2
      },
      "co_citations": [
        {
          "id": "art-63a8ce7685e1",
          "source_name": "Economedia",
          "url": "https://economedia.ro/9-kilometri-de-autostrada-au-asfalt-pe-lotul-4-al-a13-sibiu-fagaras-cum-avanseaza-lucrarile-si-drumul-de-legatura-cu-dn1.html",
          "title": "VIDEO: 9 kilometri de autostradă au asfalt pe Lotul 4 al A13 Sibiu–Făgăraș. Cum avansează lucrările și drumul de…"
        },
        {
          "id": "art-faf01db7b927",
          "source_name": "Economedia",
          "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-toate-cele-26-de-structuri-sunt-in-lucru-doua-poduri-in-arc-de-164-de-metri-provocarile-proiectului.html",
          "title": "VIDEO: Lotul 4 al Autostrăzii A13, Sibiu – Făgăraș: Toate cele 26 de structuri sunt în lucru. Două poduri în arc, de…"
        }
      ]
    },
    {
      "id": "sc-c15732c4d657",
      "title": "Top constructori autostrăzi: Makyol, Danlin XXL și Pizzarotti - Retter au avut cele mai mari progese în ultimele două…",
      "extracted_headline": "Progrese semnificative pe A13, A0, A3, A1 și A7; loturi A13 ajung peste 40% fizic",
      "summary": "Articolul raportează progrese fizice recente pe mai multe loturi de autostradă din România, cele mai mari fiind pe loturi din A13, A8 și A0.",
      "url": "https://www.economica.net/top-constructori-autostrazi-25_990095.html",
      "published_at": "2026-11-01T16:40:44Z",
      "roads": [
        "A13",
        "A8",
        "A0",
        "A3",
        "A1",
        "A7"
      ],
      "lot_id": "lot-a13-l4",
      "lot_ids": [
        "lot-a1-pit-sb-s3",
        "lot-a1-pit-sb-s4",
        "lot-a13-l1",
        "lot-a13-l2",
        "lot-a13-l4"
      ],
      "source": {
        "id": "economica",
        "name": "Economica.net",
        "trust_tier": 2
      },
      "co_citations": []
    }
  ],
  "provenance": {
    "progress_percent": {
      "source": "Economica.net",
      "tier": 2,
      "url": "https://www.economica.net/autostrada-a13-sibiu-fagaras-28_979643.html",
      "quote": "Tronsonul 4 (Sâmbăta de Sus – Municipiul Făgăraș), în lungime de 16,27 km: stadiul fizic este de 36,26%",
      "date": "2026-09-24"
    },
    "estimated_date": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-a-ajuns-la-45-relocarile-de-gaze-si-vremea-principalele-provocari-ale-santierului.html",
      "quote": "în funcție de vreme, să avem șanse să încheiem lucrarea undeva la sfârșitul lui 2027",
      "date": "2026-11-02"
    },
    "contractual_date": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-toate-cele-26-de-structuri-sunt-in-lucru-doua-poduri-in-arc-de-164-de-metri-provocarile-proiectului.html",
      "quote": "Termenul de finalizare, conform contractului ... este ianuarie 2028.",
      "date": "2026-11-03"
    },
    "contractor": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/video-lotul-4-al-autostrazii-a13-sibiu-fagaras-toate-cele-26-de-structuri-sunt-in-lucru-doua-poduri-in-arc-de-164-de-metri-provocarile-proiectului.html",
      "quote": "contractului încheiat între CNAIR și constructorul tuc Makyol",
      "date": "2026-11-03"
    },
    "contract_value": {
      "source": "Economedia",
      "tier": 2,
      "url": "https://economedia.ro/autostrada-sibiu-fagaras-cnair-semneaza-cu-makyol-contractul-pentru-lotul-4-cnsc-a-respins-contestatia-strabag.html",
      "quote": "1,19 miliarde lei, fără TVA",
      "date": "2023-07-11"
    },
    "financing": {
      "source": "Economica.net",
      "tier": 2,
      "url": "https://economica.net/top-constructori-autostrazi-25_990095.html",
      "quote": "lotul 4 din Autostrada A13 Sibiu – Făgăraș, ajuns la un stadiu fizic de 42,61%",
      "date": "2026-11-01"
    },
    "status": {
      "source": "Economica.net",
      "tier": 2,
      "url": "https://economica.net/top-constructori-autostrazi-25_990095.html",
      "quote": "lotul 4 din Autostrada A13 Sibiu – Făgăraș, ajuns la un stadiu fizic de 42,61%",
      "date": "2026-11-01"
    }
  },
  "attributed_range": null,
  "is_hand_drawn": false
}